- Introduction:
- Earliest start time (ES) - The earliest time, an activity can start once the previous dependent activities are over.
- Earliest finish time (EF) - This would be ES + activity duration.
- Latest finish time (LF) - The latest time an activity can finish without delaying the project.
- Latest start time (LS) - This would be LF - activity duration.
- Finish to Start (FS) - Later task does not start until the previous task is finished
- Finish to Finish (FF) - Later task does not finish until the previous task is finished
- Start to Start (SS) - Later task does not start until the previous task starts
- Start to Finish (SF) - Later task does not finish before previous task starts
When it comes to project activity management, activity sequencing is one of the main tasks. Among many other parameters, float is one of the key concepts used in project scheduling.
Float can be used to facilitate the freedom for a particular task. Let's have a look at the float in detail.
Float:
When it comes to each activity in the project, there are four parameters for each related to the timelines. Those are defined as:
Leads and Lags:
Leads and Lags are types of float. Let's take an example to understand this.
In project management, there are four types of dependencies:
The time between the start dates of the two tasks can be defined as a lag (2 days in this case).
If the relationship between task A and B was Finish to Start (FS), then the 'lead' can be illustrated as:
Task B started prior to Task A with a 'lead.'
Conclusion
For a project manager, the concepts of float, lead and lag make a lot of meaning and sense. These aspects of tasks are important in order to calculate project timeline variations and eventually the project completion time.
For Process Engineer, the basic concepts of scheduling is vital in ensuring that all process design related activities is carried in a planned matter without delaying the schedule.
No comments:
Post a Comment